Space Planning Projects

Current Projects at John Jay College
Capital Projects Schedule Information Links
New Building Club Row Renovation 5% Construction Full renovation of former Club row spaces
Haaren Hall Signage 5% Construction New Building signage throughout Haaren Hall
John Jay Theater Doors 95% Construction Replacement of loading doors and adjacent facade
John Jay Switchgear Upgrade Construction started Fall 2022
Haaren Hall E-Learning Lab Construction Documents New E-Learning Lab for Instructional video on Haaren 3rd Floor
Campus Doors Hold Opens Construction procurement complete New hold open devices tied to the Building Fire Alarm system
Jay Walk Railings Design Development Modifications to existing railings to increase their height
Haaren Hall Skylight & Lobby Schematic Design Renovation of Haaren Hall Lobby and skylight replacement
Haaren Hall Athletic Facility Completed 2022 Renovation of 3rd Floor Athletic Center
Haaren Hall Gym Lighting Completed 2022 New Gym lighting & controls
John Jay Atrium Beam Scope Development
John Jay Public Assembly Construction Documents
Haaren Hall Hot Water Equipment Complete 2022
Faculty Office Relocations Summer 2023
club row rendering